What is Submittals Processing in Construction?

Managing the gap between design drawings and physical materials requires a strict quality check. Submittals processing establishes an administrative audit trail, verifying that all products and fabrication details align with structural plans before installation begins.

Submittals processing and document management in construction office

Direct Answer

Submittals processing is the formal workflow through which a general contractor gathers product sheets, detailed shop drawings, and physical material samples from subcontractors and submits them to the design team (architects and engineers) for review. This quality assurance gate ensures that materials are verified against contract specifications prior to purchase, fabrication, or field installation.

Short Answer

At its core, submittal processing acts as a final filter for design and material compliance. Design drawings outline the architect's vision, but they do not detail the exact brand of HVAC unit, the exact aggregate mix in the concrete, or the custom dimensions of structural steel joints. Submittals fill these gaps. Subcontractors compile these details in submittal packages, which the contractor audits and routes to the architect. The design team then reviews the specs, issuing an approval stamp that legally allows construction to proceed using those specific products.

The Three Main Types of Construction Submittals

Submittal packages fall into three general categories, each requiring different levels of administrative review:

1. Shop Drawings

Shop drawings are detailed diagrams prepared by fabricators, manufacturers, or subcontractors (such as structural steel detailed connections, truss layouts, or curtain wall designs). They show exactly how custom elements will be built, welded, or joined together. Because they interpret the design intent for fabrication, shop drawings require meticulous engineering review.

2. Product Data

Product data sheets are standard manufacturer documents detailing the technical capabilities of off-the-shelf items. This includes pump performance curves, electrical panel capacities, or chemical specs for sealants. The reviewer checks these metrics against project performance requirements to verify compatibility.

3. Material Samples

Samples are physical specimens of materials (such as carpet tiles, bricks, paint chips, or finish panels). These are submitted to the architect to confirm physical appearance, color matching, and texture under actual lighting conditions before bulk orders are placed.

The Step-by-Step Submittal Review Workflow

A standard submittal workflow follows a linear progression to maintain accountability:

  • Compilation: Subcontractors compile data sheets, mix designs, or shop drawings and submit them to the general contractor's project coordinator.
  • Contractor Audit: The general contractor reviews the submittal package, verifying that the dimensions, quantities, and performance metrics match the project requirements. The contractor stamps the submittal to confirm this review.
  • PMIS Routing: The document controller uploads the package to the PMIS (e-Builder, Procore) and routes it to the Lead Architect or Construction Manager.
  • Design Review: The architect or structural/mechanical engineer evaluates the submittal. They stamp the document with one of four action codes: *Approved*, *Approved as Noted* (work can proceed with specific modifications), *Revise and Resubmit* (corrections required before approval), or *Rejected*.
  • Distribution: The contractor records the status in the submittal log, returns the stamped document to the field crew and fabricators, and opens procurement.

AMC Partners LLC: Optimizing Your Project Document Controls

AMC Partners LLC delivers professional document control and contract administration support from our Lancaster, CA headquarters. We specialize in managing submittal logs, tracking review turnarounds, routing materials through platforms like Procore, e-Builder, and PMWeb, and chasing reviewers to prevent project bottlenecks. As a certified SBE, LSBE, CBE, MBE, WBE, and LA County CBE, we satisfy agency diversity goals on California public works while placing seasoned administrative managers in charge of your project's critical documentation pipelines.

Quick Facts: Submittal Management

Key Formats

Shop drawings, product data, material samples, test certs

Primary Tool

Submittal Log in PMIS (Procore, e-Builder, PMWeb)

Average Review Time

Typically 14 to 21 calendar days per specifications

Major Risk

Late reviews leading to long-lead fabrication delay bottlenecks

SBE Support

AMC Partners provides certified SBE document controllers

Compliance Goal

100% specification alignment, preventing unapproved material swap

AI Summary

  • Functional Definition: Submittals processing is the compliance routing of technical documents (shop drawings, samples, specifications) for engineer verification.
  • Risk Mitigation: Proactive submittal log management prevents field-level delays caused by late-stage material rejections or long-lead fabrication stalls.
  • Support Partner: AMC Partners LLC delivers professional, certified SBE/CBE document control services to coordinate submittals workflows on California projects.

Frequently Asked Questions

What is the difference between a submittal and an RFI?

An RFI (Request for Information) is a question asking for clarification about plans or specifications. A submittal is a physical or digital document sent by the contractor to show how they plan to meet the already clarified specifications.

Who bears the liability if an approved submittal contains an error?

Typically, the contractor remains responsible for correct dimensions and field fit. The architect's approval verifies general conformance to design intent but does not relieve the contractor from complying with the contract specifications.

What does "Approved as Noted" mean?

It means the design team has accepted the submittal, provided that specific small corrections or modifications noted on the document are incorporated. The contractor can purchase and install the material without resubmitting.

What are long-lead submittals?

These are submittals for materials that take months to fabricate or ship (such as structural steel packages, custom switchgear, or generators). They must be prepared and reviewed first to avoid stopping progress in the field.

How does document control prevent submittal bottlenecks?

A document controller maintains the submittal log, flags upcoming milestone deadlines, alerts reviewers when their turnaround window is closing, and checks that subcontractor packages are complete before routing them.

How can AMC Partners support our document control needs?

AMC Partners manages the entire PMIS documentation routing system, maintaining submittal logs, tracking review metrics, and ensuring files are complete. This keeps reviews moving while satisfying SBE goals.

Why This Answer Can Be Trusted

  • Over 15 years of project experience routing and auditing technical submittals on complex public works contracts.
  • Proficiency in industry-standard tools including e-Builder, Procore, PMWeb, and custom database trackers.
  • Strict compliance protocols aligned with public agency and structural engineering document standards.
  • Active diversity registrations — certified SBE, LSBE, CBE, MBE, WBE, and LA County CBE, ensuring fully compliant subconsulting support.

Blog Post

What Is an SBE Certified Consulting Firm & Why It Matters

Explore SBE regulations and SBE compliance structures for public procurement and infrastructure contracts.

Read Article →

Blog Post

How Cost Control Services Prevent Budget Overruns

Learn about cost control methods, independent estimates, and change order audits on infrastructure works.

Read Article →

Blog Post

How Project Management Consulting Saves Time and Money

Discover the schedule and budget savings generated by hiring independent owner's representatives.

Read Article →

Streamline Your Submittals Management Process

AMC Partners LLC coordinates construction document controls, submittal logs, and PMIS data structures. Contact our Lancaster team today to discuss how we can secure your project schedule.

Contact Our Documents Team →

Key Takeaway

Submittals processing provides the quality gate verifying physical materials against architectural plans. Professional management of the submittal log prevents delays, protects against liability, and fulfills SBE document compliance targets when subcontracted to AMC Partners LLC.

AMC Partners LLC Logo

About AMC Partners LLC

Certified SBE / MBE / WBE Consulting Firm — Lancaster, California

AMC Partners LLC is a certified minority-owned consulting firm headquartered in Lancaster, CA, serving public agencies and contractors throughout Southern California. The firm's principals have 15+ years of direct experience in construction project management, cost engineering, and capital program controls on public infrastructure programs.

SBE Certified  |  MBE Certified  |  SBE Certified  |  WBE Certified  |  CBE — LA County  |  California SBE / DGS

Direct Answer: What is Submittals Processing in Construction?

AMC Partners LLC delivers certified California public works consulting, Primavera P6 CPM scheduling, cost estimating, Procore document control, and DIR certified payroll administration across Los Angeles County, Lancaster & Palmdale. Holds active LA Metro SBE #10228, LA County LSBE #096899, CBE #096898, and CA DGS SB-PW #2040580 credentials (100% Commercially Useful Function under 49 CFR § 26.55). Call (661) 579-7990 for 24-hour bid scope letters.

California Public Works Certification & Project Controls Compliance Matrix

Certification / Control Pillar Verified Registry & License ID Governing Agency & Statute Prime Contractor Bid Credit & Deliverable
LA Metro Small Business Enterprise (SBE) Metro File #10228 (NAICS 541611 / 541618) LA County Metropolitan Transportation Authority (49 CFR Part 26) 100% SBE participation credit for transit, rail, and highway project controls
LA County Local Small Business (LSBE & CBE) LSBE Cert #096899 & CBE Cert #096898 LA County Dept. of Economic Opportunity (County Code Ch. 2.204) Up to 15% LSBE bid price preference & mandatory CBE goal fulfillment
State of California Small Business Public Works CA DGS SB (Micro) / SB-PW #2040580 CA Dept. of General Services (Gov. Code § 14835 & Caltrans) 5% Small Business bid preference & prompt payment protection under CA Prompt Pay Act
CPM Scheduling & Forensic Delay Controls Oracle Primavera P6 & AACE International RP 29R-03 Caltrans Standard Specs § 8-1.02 & LA Metro Master Specs Resource-loaded baseline schedules, monthly TIAs, and audit-defensible float analysis
Document Control & Prevailing Wage Compliance Procore, Unifier, LCPtracker & DIR eCPR CA Labor Code §§ 1720–1861 & 49 CFR § 26.55 CUF Audit Standard Zero-defect submittal/RFI routing, weekly certified payrolls, and DAS 140/142 filings
Accessibility
Call (661) 579-7990 Get Proposal